Offshore Oil & Gas Future Development







Installation of SUJT-C Petronas Carigali Monopod Platform

SUJT-C Petronas Carigali Monopod Platform

  • Facility : SUJT-C Monopod
  • Owner : Petronas
  • Location : Sumandak Phase 2
  • Fabricator : Ramunia Fabricators, Teluk Ramunia Johor.
  • Installation Engineer : Abdul Wahab Said
  • Field Engineer : TBA (To Be Advise Later) from bunch of TLO Field Engineers.
  • Derrick Barge : Sea Horizon
  • Installation date : Mid Year 2007
  • Jacket Weight :
  • Topside Weight :
  • Jacket Loadout Method :
  • Topside Loadout Method :
  • Transportation : Jacket transported vertical onboard 300 or 280 class barge.
  • Risers : 3 nos
  • Pipelines connected to this platform:
      • 8″ x 5KM SUJTC to SUPG-B
      • 10″ x 5km SUJT-C to SUPG-B piggyback with 2″ x 5km SUJT-C to SUPG-B
  • No. of Risers : 3 nos.

SUJT-C is a new breed of monopod design. By referring to TL Offshore track record, The
is is the first time TLO to install such design. On Previous records shows TLO have successfully installed the Anoa Ledang Monopod (Tarpoon) which is totally different installation method.

Abdul Wahab Said, the nominated Lead Installation engineer is working hard to ensure the platform is successfully installed in a safe manner. If Malaysia Boleh n TLO also Boleh.


Posted by : Sulaiman Sabur
Biography : Author (also the WebMaster) hold a degree in Mechanical Engineering from University of Malaya. He has extensive experience in offshore construction and currently employed by one of the Major Offshore Construction Company in Malaysia.

How to post your own article << Click Here !


6 Responses to 'Installation of SUJT-C Petronas Carigali Monopod Platform'

Subscribe to comments with RSS

  1. asrul said,

    on 28th, August

    assalamualaikum..
    bleh sapa2 bagitu berapa berat topside sumandak ni?

  2. asrul said,

    on 3rd, September

    hello, is there anybody can help me with this?

  3. Mohd Azwan said,

    on 3rd, September

    W’salam..
    En. Asrul,
    I was a part of the team involved for this SUJT-C platform installation. If i’am not mistaken the weight of the jacket and topside are 610 MT and 508 MT respectively.

  4. asrul said,

    on 4th, September

    dear En Azwan,
    thank you for your information.Actually i`m doing my final project and need to gather the information about this monopod. so may i have your email because i think you are the best person to ask about this. my email is asrul_marine@yahoo.com.my

  5. Mohd Azwan said,

    on 8th, September

    Asrul,

    U can reach me at mazwan@crest.com.my. Anything, u can just email me or post a message here. So, is there anything that I can help u?

  6. aie said,

    on 18th, October

    hiii
    i like to know is there has vacancy as diesel mechanic or such of maintenance?
    im 10 years marine crew experience in offshore marine.
    works as diesel mechanic cum fitter.

Websites Linked to this Article

Leave a Reply

Latest Comments


subscribe to offshore oil and gas news

SUBSCRIBE to Latest Posts by Email


Your email is safe from spam. All emails will be handled by FeedBurner a Google Company.
Subscribe Safely NOW