Loadout of SUJT-C Monopod Jacket
Remember last time i wrote about some detail of this SUJT-C jacket here >> Installation of SUJT-C Monopod Platform. Below is very interesting video taken during loadout of this jacket. One thing that unique about the operation is, the jacket was loaded & transported vertically offshore. Enjoy video & tell us what do you think?
| Posted by : Sulaiman Sabur | |
| Biography : Author (also the WebMaster) hold a degree in Mechanical Engineering from University of Malaya. He has extensive experience in offshore construction and currently employed by one of the Major Offshore Construction Company in Malaysia. |
How to post your own article << Click Here !
2 Responses to 'Loadout of SUJT-C Monopod Jacket'
Websites Linked to this Article
Leave a Reply
![]() SUBSCRIBE to Latest Posts by EmailYour email is safe from spam. All emails will be handled by FeedBurner a Google Company. Subscribe Safely NOW |


on 2nd, July
interesting!!!!
on 8th, September
It took almost a day to load out the jacket onto the barge vertically by boogie. It was in May 2007. The platform was succesfully installed in July 2007 by two derrick barges, DB Sea Horizon and DB SP1. This project was succesful led by SFE Wahab Said assisted by TLO’s FEs.