Offshore Oil & Gas Future Development







Offshore Engineers Trainning Plan (Structure)

Operation Daily Progress Meeting

Part of engineers jobs is to plan, execute and present the operation progress to client every morning.  Picture taken during Daily Progress Meeting in DPDSV Miss Marie bridge.

ENGINEERS TRAINING CHECKLIST

1. Familiarity with equipment on derrick barge.

Describe the use of the equipment below and understand how it works, and what are the necessary procedures and/or precautions thaht are required for its operation, if any.

Schematics/Sketches/Layout of equipment if available.

  • Installation Equipment
  • Communication Equipment
  • Navigation Equipment
  • Positioning Equipment
  • Beacon or Transponder on Anchor
  • Support Facilities
  • Diving Facilities
  • Survey Equipment
  • Safety Facilities
  • Pulling Winches
  • R.O.V System
  • D.S.V
  • Anchor Handling Capabilities of Vessel
  • Anchor Tracking Equipment
  • Acoustic Positioning Systems
  • Radio Positioning Systems

2. Familiarization with

  • Design of Padeyes Lifting Slings
  • Hooks
  • Shackles
  • Offshore Rigging Platforms
  • Loadout Stability
  • Seafastening/tie down details
  • Transportation Analysis.
  • Environmental Conditions
    • Wind Direction, Force
    • Wave Magnitude
    • Draft at Loadout Quay.

3. Familiarise with Major Procedures and Reports

3.1 Transportation and Loadout

3.1.1 Barge Arrangements/layout

  • Seafastening & Tie-Down Design
  • Tow Analysis
  • Specifications Used

3.1.2 Rigging Procedure for All Types of Lifting.

  • Sling and Shackle Rigging System
  • Certification and Testing of Sling and Shackles.

3.1.3 Transportation and Seafastening Design Report.

  • Barge Transportation and Seafasterning Analysis and Tug Boat Bollard Pull Capacity.
  • Seafastening Design Calculations.
  • Barge Strength and Stability Checks
  • Seafastening Drawings
  • Seafasterning Materials (MTO) and wastages and over lengths.
  • Towing Bridle Selection/Design and Calculations.
  • Route Survey/Map and Identified Shelter Locations.

3.2 Installation Of Structures.

3.2.1 Jacket Installation Analysis/Procedure

3.2.2 Jacket Lift Analysis/Procedure.

  • Lifting Rigging Arrangement.
  • Third Party Certification for Sling and Shackles.
  • Calculation of Sling Analysis, Sling Tensions (3 out of 4 slings operative)
  • Sling/Shackle Safety Check.
  • Jacket Structural Integrity Check.
  • Seafastening Cutting Sequence
  • Lifting Criteria
  • Derrick Barge/Transportation barge setups
  • Jacket Tilt Angle During Lift.
  • Lift Radius, Lift Weight and Required Hook Height Super Imposed on Crane Lift Charts.

3.2.3 Jacket Upending Analysis/Procedure.

  • Jacket Weight, Displacement and Buoyancy Calculations.
  • Upending Rigging Arrangement.
  • Upending Sling Tension per each Upending Step.
  • Upending Sling and Shackle Safety Factor.
  • Upending Padeye Check.
  • Sling/Shackle 3rd Party Certification.
  • Controlled Flooding Sequence/Procedure of Jacket Legs/Buoyancy Tanks (if any).
  • Hook Radius, Load and Height at Each Upending Stage Superimposed on Crane Lift Chart.
  • Jacket Angle on Each Stage of Upending.
  • On-bottom Weight Calculations and Madman Adequacy Check.
  • Medical Clearance at Each Upending Stage.

3.2.4. Pile Driving Engineering.

  • Pile Driving Engineering Report.
  • Stability of structure against overturning during piling. Verify pile stick-up length for pile hammers.
  • Method of pile lifting and upending. Calculations to prove methods do not overstress piles.
  • Pile refusal/acceptance criteria based on expected pile stress and designed ultimate bearing capacity of pile.
  • Predictions.
    • Pile self penetration (Self weight and with first hammer in proposed piling sequence)
    • Pile Driveability analysis by specialist Geotechnical Engineer.
  • Recommendation:
    • Hammer to be used (from self pen. To target pen)
    • Pile Driving sequence.
    • Retrieve Procedures – premature refusal of insufficient bearing capacity.
  • Soil Resistance to driving taking into account plugged conditions as appropriate.
  • Hammer blow count w.r.t penetration.
  • Effect of delays in driving.
  • Effect of variation in hammer efficiency based on typical range of hammer efficiencies.
  • Pile stresses during driving.
  • Effect of utilization of driving stress if required.

Above predictions to be made for the range of hammer proposed.

3.2.5 Pile Monitoring Procedure

  • Specialist geotechnical consultant proposed.

CV of personnel proposed for pile monitoring.

  • Pile monitoring equipment spread.
  • Data analysis and interpretation methodology.
  • Operational aspects of installing instrumentation, data acquisition and removing instrumentation.
  • Equipment/Instrument calibration.
  • How pile monitoring data will be used to control pile driving.

Within 1 hour after driving.

  • Pile driving analysis print out.
  • Pile adequacy assessment – after driving to target penetration after refusal at any other penetration.
  • Recommendation of remedial action, if any.

3.2.6 Post-Installation Pile/Conductor Driving Monitoring Report.

  • Summary s.o.w.
  • Pile/Conductor adequacy conclusion with support calculations.
  • Result of PDA pile/conductor Monitoring.
  • Hammer preference summary with hammer nos for tractability.
  • Pre-installation analysis/procedures for interpretation of field measurements.
  • Predicted vs. Actual pile/conductor Driving behavior.
  • Instrumentation + Monitoring Equipment + Procedures + Calibration reports + Correction factors.
  • Log kept by pile monitoring engineer highlighting significant events during pile driving.

3.2.7 Topside installation engineering

Topside lift analysis/procedure.

  • Lifting rigging requirement.
  • Sling/shackle certification from 3rd party surveyor. (<6 months prior to planned installation)
  • Topside installation engineering report.
  • Calculation of sling, padeye orientation based on latest COG.
  • Calculations of sling tensions assuming 75/25 load distribution to opposite fair of slings.
  • Sling/shackle safety factor.
  • Padeye strength check.
  • Deck structural lategnity check (if required)
  • Limiting criteria for lifting.
  • Derrick + Transportation Barge Set-ups.
  • Attitude of topside during lift (Ë of lift)
  • Lift radius, weight and required hook height superimposed on crane lift chart.
  • Upgrading lift analysis.

3.3. Anchor Handling.

Detailed anchor handling procedures and anchoring patterns with due to consideration to avoid damage to existing facilities by anchors and / or anchor cables.

3.4 Survey Positioning System

  • Echo soconder
  • Side scan sonar.
  • Pipeline.
  • Theodolite.
  • EDM (complete at prism)
  • Handheld GPRS receiver
  • Level and staff
  • Flugate compasses
  • Mean sea level measurement Device
  • Acoustic Tracking system.
  • Data processing equipment.

3.5 Scaffolding

3.6 Rigging + Sling Material

3.7 Gangway

3.8 Diving Equipment.

3.9 NDT Equipment

3.10 Stores

3.11 Barge Data

  • Uniform deck load longitudinal bulkhead
  • Line load along transverse bulkhead.
  • Point load along longitudinal bulkhead
  • Point load along transverse bulkhead.
  • Point load at intersection and transverse bulkheads.
  • Line load

3.12 Barge Inspection.

  • Actual Ballast Pump Capacity (built-in + supplementary ballast pump)
  • Level and straighten of skid beams/launchways.
  • Towing bridle and associated fittings.
  • Function test on launching system
  • Rocker beam rotation.
  • Function test on all navigation aids.

3.13 Jacket Installation

  • Pre-post installation survey.
  • Lift Jacket-check diaphragms intact.
  • Upend jacket.
  • Place jacket.

3.14. Pile Installation.

  • Install pile.
  • Lift + upend files.
  • Stabbing and driving sequence procedures.
  • Monitor pulling activity.
  • Drive piles to target penetration.
  • Pile Driving Records.
    • Hammer used
    • Hammer monitoring data
    • Pile identification.
    • Blow count vs. penetration
    • Time
    • Pile monitoring data.
    • Reason for stoppages if any.
  • Pile restrict test.
  • Soil resistance to driving.
  • Magnitude of maximum pile stresses during driving.
  • Hammer blow for foot of penetration.
  • Hammer stroke.
  • Hammer blow rate.
  • Hammer efficiency.
  • System efficiency.

At end of driving if pile meets acceptance criteria.

  • Find blow count for fast of penetration
  • Hammer and system efficiency.
  • Soil resistance to driving.

If pile/conductor does not meet acceptance criteria at target penetration depth provide a recommendations on remedial action.

Pile monitoring during the restrict test provide.

  • Final blow count per foot of penetration.
  • Hammer and System efficiency.
  • Soil resistance to driving.

If pile meets premature refusal provide.

  • Final blowcount per foot of penetration
  • Hammer and System Efficiency.
  • Soil resistance to driving.
  • Recommendations of remedial action.

3.14 Conductor installation.

Conductor driving.

  • Hammer used
  • Hammer monitoring data.
  • Conductor identification.
  • Blow count vs. penetration (blow/ft)
  • Time
  • Conductor monitoring data.
  • Reason for stoppages if any.

3.15 Conductor and Hammer Monitoring.

3.16 Boatlanding and Riser Guard Installation.

3.17 Topside Installation.

  • Cut jacket transition.
  • Lift, Low and Place Topside.

3.18 Micellaneous installation.

  • Stairways.
  • Grating
  • Miscellaneous platform.
  • Conductor spools
  • Rigging platform removal.

3.19 Vent Boom Installation.

  • BLOG IN BAHASA

Siapa siapa rasa nak jadi Offshore field engineer. Terutamanya structure, benda kat atas ni le yg korang kena tahu. Kepada engineer yg dah lama tu, boleh le go through list ni untuk buat ’self check’. Nanti bila aku ada masa aku share pulak trainning plan untuk pipeline engineer… tu kena carik dalam koleksi aku, memakan masa jugak tu… ok selamat untuk semua. Yang penting kita pastikan TEMPAT KERJA YANG SELAMAT!


Posted by : Sulaiman Sabur
Biography : Author (also the WebMaster) hold a degree in Mechanical Engineering from University of Malaya. He has extensive experience in offshore construction and currently employed by one of the Major Offshore Construction Company in Malaysia.

How to post your own article << Click Here !


10 Responses to 'Offshore Engineers Trainning Plan (Structure)'

Subscribe to comments with RSS or TrackBack to 'Offshore Engineers Trainning Plan (Structure)'.

  1. Sukri said,

    on 3rd, April

    Hi guys,
    Thanks for nice photos & comments. I wish to join offshore line but have no luck so far. Anyway, it’s good to know some about offshore stuffs!

  2. asrul said,

    on 23rd, September

    akum…
    i like to apply for the offshore fied engineer that you post in this blog. can you tell me where should i submit my resume.

    asrul_marine@yahoo.com.my

  3. nik mohd farid said,

    on 10th, August

    salam.

    can u suggest to me which company should i apply for my industrial training (internship) programme as i’m very interested in the oil and gas industry, particularly working in the offshore.

    thank you.

  4. fe.azwan said,

    on 16th, January

    it’s a complete list for structure installation. manyak wooo…penat jgk nak hafal tuu..

  5. damn said,

    on 8th, July

    bro sulaiman,
    i am very familiar with point no 2 and 3.1 ONLY :) but anxiously want to learn and experience more on the other points. How do i find the opportunity to do this? is there any way i can contact you?

    tolong laa hamba, tuan hamba yang budiman.. :p

  6. Ganesh Sidharth K said,

    on 21st, October

    Dear Suleman Sabur,

    Thank you very much for writing this blog about role & responsibility of an FE in offshore industry.

    I have completed one year in installation work in offshore and was searching such a blog since then.
    It is truly informative and covering all the points which any FE would like to know.

    Thanks a lot once again.

    Take care.
    Have a nice day.

    Rgds,
    Sidhu

  7. on 27th, October

    Thank you for the visit. WIll keep the blog updated and will write more from time to time.

Websites Linked to this Article

  1. Oil Gas Jobs : Offshoreman BLOG » Vacancy for Offshore Field Engineer Positions in SapuraCrest Petroleum
  2. » Vacancy for Offshore Field Engineer Positions in SapuraCrest Petroleum · Offshore Oil & Gas Future Development
  3. » SapuraCrest Petroleum Job Vacancies - Junior Field Engineer · Offshore Oil & Gas Future Development

Leave a Reply

Latest Comments


subscribe to offshore oil and gas news

SUBSCRIBE to Latest Posts by Email


Your email is safe from spam. All emails will be handled by FeedBurner a Google Company.
Subscribe Safely NOW