Subsea Pipeline Installation (S-Lay) & Beach Pull (Shore Approach)

Joint 1493 Leaving last station (Mastic Dope Station) towards Stinger
This is a generic Content for Fixed Offshore Pipelay Installation Procedure. As a field engineer, developing of this kind of procedure is part of my daily job in the office. I hope this section will help you to get the picture how the subsea pipeline were installed. I’ll try to write in a very simple way just to ensure any layman will get the brief view on how the pipeline installed offshore. I’m not going to write the actual procedure! Just in form of narrative.
(All procedures are belong to the COMPANY & if you require a sample, please go through the proper channel)
Introduction
Description of Pipeline
Scope/Sequence of Work
Installation Summary
Reference Documents
Contractor Documents
Client Approved Drawing For Construction
Pipeline Schematic Diagram
Overall Field Layout
LOAD-OUT AND TRANSPORTATION
Pre-Loadout
Loadout and Transportation
Figures
Loadout No. 1 (Voyage No. 1) on 280 Ft Class Barge (Example Sealink Pacific 287)
3.0 BEACH PULL PROCEDURE
Survey and Positioning
Barge Set-up and Anchor Moves
Preparation For Pipe Pull
Transfer of Pull Cable from the Beach
Beach Pull Buoyancy and Strip-out Cable Installation
Beach Pull Commencement
Beach Pull Activities
Stripping Out Buoyancy Tanks
Beach Pull Completion Activities
Pipeline Beach Pull General Arrangement
Beach Pull Anchor Pattern
Beach Pull Start-up Head at
Buoyancy Tank Detail For Beach Pull Activity
Derrick Crane Strip-out of Buoyancy Tank
START-UP PROCEDURE ( DEADMAN ANCHOR/BOWSTRING)
Equipment List and Preparations
Equipment List for Start-up at Onshore Terminal
Preparations for Start-up at Onshore Terminal
Detailed Procedure
Detailed Procedure for Start-up at LCOT for 20†dia. pipeline
Extracts from Field Data Book
Barge Setup for Start-up of 20†dia.
Deadman Start-up Head
Deadman Anchor Start-up Rigging Arrangement at Onshore Terminal
DMA Deployment Sequence
Barge Set-up in Relation to Pulling Head Location
PIPELAYING PROCEDURE
Equipment List and Preparations
Material and Equipment List For Pipelaying
Preparations for Pipelaying
Detailed Procedure
Barge Ramp and Stinger Details
Pipelay Barge Arrangement
Barge and Anchor Set-up
Pipelay Variables
Survey and Positioning
Linepipe Handling
Linepipe Preparation
Welding/NDT/Weld Repair
Welding
NDT
Weld Repair
Buckle Detection
Field Joint Coating
Serviwrap Application
Mastic Addition
Extracts from Field Data Book
Barge Roller Height and Longitudinal Distance
Alpha Pontoon Stinger Roller Heights & Distance Setting
Alpha Pontoon Stinger Roller Heights & Distance Setting
Pipe Ramp Arrangement DB 264
DLB 264 (Example) Aft, Mid and Fwd Draft
DB 264 (Example) Plan and Profile.
Sling Arrangement for Linepipe Handling
Pipe Tally Sheet Pro forma
Buckle Detector And Stop Trolley Assembly
Internal Line-up Clamp and NDT Crawler Set-up
Internal Line-up Clamp and NDT Crawler Stop Trolley Operation
Stop Trolley / Buckle Detector Cable Make-upApplication of M30B Serviwrap
Application of Marine Mastic
PIPELINE LAYDOWN/ABANDONMENT & RECOVERY
Equipment List and Preparations
Laydown Procedure
Abandonment Procedure
Recovery
Extract from Field Data Book
Laydown Head
Emergency Laydown Head
Choker Slings Arrangement
Barge Anchor Pattern Laydown Approach at Platform
Pipeline Abandonment and Recovery Step by Step
Pipeline Buckle
Preparations and Equipment List
Minor Dry Buckle
Severe Dry Buckle
Wet Buckle
START-UP/LAYDOWN HEAD PADEYE CALCULATION
BEACH PULL CALCULATION
| Posted by : Sulaiman Sabur | |
| Biography : Author (also the WebMaster) hold a degree in Mechanical Engineering from University of Malaya. He has extensive experience in offshore construction and currently employed by one of the Major Offshore Construction Company in Malaysia. |
How to post your own article << Click Here !
4 Responses to 'Subsea Pipeline Installation (S-Lay) & Beach Pull (Shore Approach)'
Websites Linked to this Article
Leave a Reply
![]() SUBSCRIBE to Latest Posts by EmailYour email is safe from spam. All emails will be handled by FeedBurner a Google Company. Subscribe Safely NOW |

on 2nd, August
bro,
bila nak tulis pasal ndt?
tulis la..byk orang nk tau..
on 24th, August
Bro,
Can u explain bout the startup and laydown calculation, and the procedures involve during those time. Im new in offshore. Both selalu lari dari target box.
thnks
on 27th, October
start up and laydown analysis can be done utilizing offpipe. Should not face any problem off the target box. its 5m x 5m min. anyway…